datacenter

Pharmaceutical Industry DEMO SA

Pharmaceutical Industry DEMO SA

Contractor: CABLETEC

Project Budget: 400.000,00 €

Duration of Construction: 10 months

Construction Year: 2021-2022

Project Description

Construction of electrical installations in new buildings (5000sqm) at the Kryoneri, Attica, with the following detailed works:

  • Installation works in order to provide electric power supply of lighting, power sockets and air conditioning equipment
  • Installation works in order to provide electric power of electric panel (Normal power – UPS power – HZ power)
  • Supply and installation works of electrical panels
  • Modification works of building΄s Main Low Voltage Panel 3000A
  • Installation and connection works of cabling and equipment for BMS System operation
  • Installation works in order to provide the power supply at ΄΄clean rooms΄΄ departments
  • Supply and installations works of low voltage cablings for the building  security and protection systems (fire detection – alarm system – access control – cctv – interlock)
  • Supply and Installation of structured cabling in order to create a data network using copper and fiber optic cables
  • As Built Drawing and measurements according to HD 384

Project Info

test