Contractor: AGT SA

Project Budget: 200.000,00 €

Duration of Construction: 6 months

Construction Year: 2023

Project Description

Electrical works installations at the taxi vehicles parking area and new Electrical works installations of the Everest fast food store with the following detailed works:

  • Installation works in order to provide the electric power supply of the indoor and outdoor lighting, the power sockets ,ventilation and the air conditioning equipment’s
  • Installation works in order to provide electric power of electric panel (Normal power – UPS power – HZ power)
  • Installation and connection works of local electrical panels
  • Supply and installations works of the low voltage cablings for specific security and protection systems (fire detection – alarm system – access control-CCTV-public address )
  • Supply and installations works of the cablings infrastructure using metal cable tray , plastic cable trucking , pipes etc
  • Supply and installations works of the underground cablings infrastructure using heavy type piping.
  • Supply, installation, termination and certification of building structured cabling in order to create a new data network using cooper and fiber optic cables.
  • Supply and installations works of the low voltage cablings for the new taxi priority system.
  • Installation and commissioning works of new systems
  • As Built Drawing and measurements according to HD 384