Construction of electrical installation building works of UNIC
Construction of electrical installation building works of UNIC
Budget: 710.000,00€
Duration of construction: 5 months
Year of construction: 2025
Construction of the building electrical installation works which are began in fall 2025 at the 12,500-square-metre facility adjacent to The Ellinikon development and consist of following works
Electrical power feeder cabling in order to provide power consumption to lighting – power sockets and air-conditioning system of the building.
Electrical power feeder cabling in order to provide power consumption to new switchboard panels of specific building levels
Installation and connection works to new switchboard panels of specific building levels
Installation cabling works of the building fire detector system
Installation cabling works and the connection of the building BMS equipment
Installation cabling works and the connection of the building CCTV equipment
Installation of structure cabling works (cooper and fiber optic) and the connection of the IT&T equipment
Installation , connection and activation of light fixture equipment
Testing and commissioning of the entire new cabling installation works
As building drawings and testing according to HD384 standard.