datacenter

Renovation and upgrading of Data Center infrastructure at BLD 11 of Athens Airport

Renovation and upgrading of Data Center infrastructure at BLD 11 of Athens Airport

Contractor: CABLETEC

Project Budget: 220.000,00 €

Duration of Construction: 7 months

Construction Year: 2021

 

 

Project Description

Construction of new electric power supply in the existing Data Center of Athens Airport in cooperation with Commscope.

  • Construction of underground cabling infrastructure
  • Modification and new installation of interconnecting copper and optical fiber cabling
  • Installation of new cabling infrastructure system using mesh cable tray in order to provide the interconnection cabling route between IT racks.
  • Software configuration and users training

Project Info

test