datacenter

Montessori children’s school building

Montessori children’s school building

Contractor: PROJECTING AND SOUND ART

Project Budget: 170.000,00 €

Duration of Construction:  7 months

Construction Year: 2020-2021

Project Description

 Construction of new electrical installations works at two (2) independent levels + building roof (2.200sqm) at Glyfada, Attikis, with the following detailed works:

  • Installation works in order to provide the electric power supply of the building lighting, the power sockets ,ventilation and the air conditioning equipment’s
  • Installation works in order to provide electric power of electric panel (Normal power – UPS power – HZ power)
  • Installation and connection works of local electrical panels
  • Supply, installation and connection of lightning protection system on the building roof.
  • Supply , installation and connection of cabling in order to make the building lighting control with  new Creston systems for the indoor lighting system using local control panels and motion detectors .
  • Supply and installations works of the low voltage cablings for security and protection systems (fire detection – alarm system – access control-CCTV )
  • Supply, installation, termination and certification of building structured cabling in order to create a new data network using cooper and fiber optic cables.
  • Supply and installations works of the cablings infrastructure using metal cable tray , plastic cable trucking , pipes etc
  • Supply and installation of IT cabinets (racks 19’’)
  • Installation and connection works of cabling and equipment for BMS System operation
  • Installation and connection works of power generator equipment
  • Installation and connection works of UPS equipment
  • Installation and commissioning works of new systems
  • As Built Drawing and measurements according to HD 384